Test run and commissioning will be executed in the following procedure:

  • cleaning the plant
  • dry run test to inspect the integration of equipment, rotation of motors,  etc.
  • water test simulates the production by using  water as media
  • product  test run the plant with the actual material as the production being.
  • taking-over test shall be carried out in the presence of the Client and INTEGRA, or their authorized representatives.